Contents

1                      Introduction                                                                          

1.1                   Purpose of the Report                                                     

1.2                   Structure of the Report                                                

2                      Project Information                                                          

2.1                   Background                                                                           

2.2                   Works Programme and Works Locations              

2.3                   Construction Activities                                                   

2.4                   Status of Environmental Approval Documents 

3                      Environmental Monitoring                                             

3.1                   Cable Installation Water Quality Monitoring    

3.2                   Marine Mammal Observation                                          

3.3                   Coral Monitoring                                                                

3.4                   Site Inspection and Audit                                                 

4                      Site Inspection Results                                                    

5                      Environmental Non-Conformance                             

5.1                   Summary of Environmental Non-compliance        

5.2                   Summary of Environmental Complaint                    

5.3                   Summary of Environmental Summon and successful prosecution     

6                      Future Key Issues                                                                

6.1                   Key Issues for the Next Reporting Period             

6.2                   Monitoring Schedule for the Next Reporting Period    

7                      Conclusions                                                                           

 


LIST OF TABLES

 

Table 2.1        Summary of Landing Point Construction Activities Undertaken during the Reporting Period

Table 2.2        Summary of Current Environmental Licensing, Notification and Permit Status

Table 6.1        Construction Works to Be Taken For the Next Reporting Week

 

 

LIST OF ANNEXES

 

Annex A         Proposed ASE Submarine Cable System (Layout Plan)

Annex B         Location of ASE Landing Point and Terrestrial Cable Route

Annex C         Completed Site Inspection Log

Annex D         Photographic Records on Site

 

EXECUTIVE SUMMARY

NTT Com Asia (NTTCA) proposes to install a telecommunication cable (Asia Submarine-cable Express (ASE) cable) of approximately 7,200 km in length, connecting Japan and Singapore with branches to the Philippines, Hong Kong SAR (HKSAR) and Malaysia.  A Project Profile (PP-452/2011) which includes an assessment of the potential environmental impacts associated with the installation of the submarine telecommunications cable system was prepared and submitted to the Environmental Protection Department (EPD) under section 5.(1)(b) and 5.(11) of the Environmental Impact Assessment Ordinance (EIAO) for the application for Permission to apply directly for Environmental Permit (EP).  The Environmental Protection Department, subsequently issued an Environmental Permit (EP- 433/2011). 

This is the First Weekly Site Inspection Report that presents the findings of the site inspection and other EM&A activities undertaken during the period from 4 to 7 October 2012.  

Environmental Site Inspection

A weekly joint environmental site inspection was carried out by the representatives of the Contractor, the Environmental Team (ET) and NTTCA.  Environmental performance complied with the environmental requirements and all necessary mitigation measures were properly implemented.

Marine Mammal Observation

Daily marine mammal exclusion zone monitoring was not carried out in the reporting period as the cable installation works in Zone C and from C to the boundary of HKSAR waters has not started.

Summary of Breaches of Action/Limit Levels

Per plan, no marine water quality monitoring was conducted in the reporting period.  Thus, no exceedances of Action and Limit Levels for water quality were recorded during the reporting week.

Environmental Complaints, Non-compliance & Summons

No non-compliance with PP recommendations, EP conditions and other requirements associated with the construction of the Project was recorded in this reporting period.

No environmental complaint was received in this reporting period.

No environmental summons was received in this reporting period.


Upcoming Works for the Next Reporting Period

Works to be undertaken in the coming monitoring period include cable laying works in Zone A, seawall duct work, land duct laying works and beach manhole construction. 

Potential environmental impacts arising from the above construction activities are mainly associated with marine water quality, dust, construction noise and waste management.

 

1                                            Introduction

ERM-Hong Kong, Limited (ERM) was appointed by NTT Com Asia (NTTCA) as the Environmental Team to conduct regular site inspections and audit the implementation of all environmental monitoring and mitigation measures recommended in the Project Profile (PP) (Register No. PP ¡V 452/2011) for the Proposed Asia Submarine-cable Express (ASE) ¡V Tseung Kwan O (the Project).

1.1                                      Purpose of the Report

This is the First Weekly Site Inspection Report (the Report), which summarises the inspection findings for the period from 4 October 2012 to 7 October 2012 and the implementation status of the EM&A recommendations on environmental protection and pollution control mitigation measures and monitoring.

1.2                                      Structure of the Report

The structure of the Report is as follows:

Section 1 :  Introduction

Details the scope and structure of the Report.

Section 2 :  Project Information

Summarises background and scope of the Project, site description, construction programme, the construction works undertaken and the status of Environmental Permits/Licenses during the reporting period.

Section 3 :  Environmental Monitoring

Summarises the monitoring programmes as recommended in the PP and the monitoring undertaken during the reporting period.

Section 4 :  Site Inspection Results

Summarises the findings of the weekly site inspection undertaken within the reporting period.

Section 5 :  Environmental Non-conformance

Summarises any exceedances of environmental performance standard, environmental complaints and environmental summons received within the reporting period.

Section 6 :  Upcoming Works for the next Reporting Period

Summarises the impact forecast and monitoring schedule for the next reporting week.

Section 7 :  Conclusions

2                                            Project Information

2.1                                      Background

NTT Com Asia (NTTCA) proposes to install a telecommunication cable (Asia Submarine-cable Express (ASE) cable) of approximately 7,200 km in length, connecting Japan and Singapore with branches to the Philippines, Hong Kong SAR (HKSAR) and Malaysia.  NTTCA is responsible for securing the approval to land the ASE cable in Tseung Kwan O, Hong Kong SAR (HKSAR).  The proposed landing site will be at a new Beach Manhole (BMH) and ultimately connect with a Data Centre in Tseung Kwan O (TKO) Industrial Estate which is scheduled for completion in 2012.  It should be noted that Tseung Kwan O is currently the landing site for a number of submarine cables.  From Tseung Kwan O, the cable will extend eastward approaching the Tathong Channel.  Near to Cape Collinson, the cable is approximately parallel to the Tathong Channel until north of Waglan Island where the cable travels eastward to the boundary of HKSAR waters where it enters the South China Sea.  The total length of cable in Hong Kong SAR waters is approximately 33.5 km.  A map of the proposed cable route is presented in Annex A.

A Project Profile (PP-452/2011) which includes an assessment of the potential environmental impacts associated with the installation of the submarine telecommunications cable system was prepared and submitted to the Environmental Protection Department (EPD) under section 5.(1)(b) and 5.(11) of the Environmental Impact Assessment Ordinance (EIAO) for the application for Permission to apply directly for Environmental Permit (EP).  The Environmental Protection Department, subsequently issued an Environmental Permit (EP- 433/2011). 

Under the requirements of Condition 2.4 of the EP, an EM&A programme as set out in the revised Environmental Monitoring and Audit Manual (EM&A Manual) is required to be implemented.  The EM&A programme includes water quality monitoring, marine mammal observation, coral monitoring and weekly site inspection. 

2.2                                      Works Programme and Works Locations

The location of the cable installation works within the boundary of Hong Kong SAR waters is shown in Annex A, while the location of the landing point (ie new Beach Manhole (BMH) in TKO Industrial Estate) is shown in Annex B.  The preliminary construction programme of the Project is given in Figure 2.1.

Figure 2.1       Preliminary Construction Programme

2.3                                      Construction Activities

Submarine Cable Installation

There are no submarine-cable installation works during the reporting period.

Landing Point Construction

The construction works of the landing point commenced on 4 October 2012 and are temporarily scheduled to be completed in early December of 2012.  A summary of the major construction activities undertaken on the landing point during the reporting period is shown in Table 2.1. 

Table 2.1        Summary of Landing Point Construction Activities Undertaken during the Reporting Period

Construction Activities Undertaken

¡P          Install fence at seawall side

¡P          Install Fence at Yi Feng

¡P          Mobilization of marine and land equipment for seawall construction

¡P          Installation of silt curtain at seaside

¡P          Removal of seawall rock armor

¡P          Installation of silt markers and settlement check points

2.4                                      Status of Environmental Approval Documents

A summary of the relevant permits, licences, and/or notifications on environmental protection for this Project is presented in Table 2.2.

Table 2.2        Summary of Current Environmental Licensing, Notification and Permit Status

Permit/ Licences/ Notification

Reference

Validity Period

Remarks

Environmental Permit

EP-433/2011

Throughout the construction and operation of the Project

Permit granted on 20 December 2011

 

 

Construction Noise Permit

GW-RE0774-12

18 Sep 2012 ¡V 31 Jan 2013

Permits granted on using of registered powered mechanical equipment for 07:00-23:00 hrs on general holidays (including Sundays) and 19:00-23:00 hrs on any day not being a general holiday for Sub-marine cable laying works of the Project

3                                              Environmental Monitoring

3.1                                      Cable Installation Water Quality Monitoring

Baseline water quality monitoring was completed by the end of September 2012.  Baseline Water Quality Monitoring Reports for Zone A, Zone B and Zone C were submitted on 19 September 2012, 25 September 2012 and 1 October 2012, respectively.

No impact water quality monitoring was conducted during the reporting period as the cable laying works has yet to commence.  Mitigation measures to control water quality pollution as recommended in the PP will be checked in due course and summarised in the Weekly Water Quality Impact Monitoring Reports.

3.2                                      Marine Mammal Observation

Daily marine mammal exclusion zone monitoring is required to be conducted during the cable installation works taking place in daylight hours along the section outside Zone A to Zone B (ie Zone C and from C to the boundary of HKSAR waters).  This monitoring was not carried out in the reporting period as the cable installation works in Zone C and from C to the boundary of HKSAR waters has not started. 

3.3                                      Coral Monitoring

Baseline coral monitoring was completed in September 2012.  The Baseline Coral Monitoring Survey Report was submitted on 28 September 2012.  Post-project coral monitoring will be conducted within one month after completion of the jetting works, with the Post-project Coral Monitoring Survey Report to be submitted within one month after completion of the marine works.  Impact monitoring for coral during cable installation works is not required under the Project. 

3.4                                      Site Inspection and Audit

In accordance with the revised EM&A Manual, a weekly site inspection should be undertaken at the landing point (ie new Beach Manhole (BMH) in TKO Industrial Estate) to ensure that the appropriate environmental protection and pollution control mitigation measures are properly implemented in accordance with the Project Profile (PP-452/2011).  Results of the site inspection in the reporting period are provided in Section 4.

4                                              Site Inspection Results

The weekly site inspection is required to be carried out by the representatives of the Contractor and the Environmental Team (ET).  A Site Inspection Log is completed by the ET representative to record whether the Contractor is compliant with environmental regulations such as noise, water quality and housekeeping etc (Annex C).

During the reporting period, the site inspection was conducted on 5 October 2012 by the representatives of the Contractor, the ET and NTTCA.  There was no non-compliance recorded during the site audit.  Major findings and recommendations are summarised as follows:    

(i)         A copy of EP was displayed conspicuously at the vehicular site entrance in accordance with the requirement of Condition 1.5 of the EP. (Annex D Photo No. 1)

(ii)        A silt curtain was employed around the seawall area in order to reduce the dispersion of sediments from the landing site (Annex D Photo No. 2).

(iii)       Spillage containment such as dip tray was found to have been provided for the equipment (eg generator), which potentially has oil leakage (Annex D Photo No. 3).

(iv)      Housekeeping of the construction site was observed to have been conducted in a proper way.  A portable toilet has been placed on site (Annex D Photo No. 4), and general refuse was not frequently found.  The Contractor was nevertheless recommended to provide enough rubbish bins within the construction site for better rubbish disposal.  Following-up actions by the Contractor will be checked in next week¡¦s site inspection.

(v)       An idling excavator was observed during the site inspection.  The Contractor was reminded to turn off all equipment/ vehicles when they are not actively in use.  The excavator was turned off by the Contractor immediately after the recommendation.

(vi)      The Contractor was suggested to display labels stating the sound power level in dB on all major PME.  The corrective action was being undertaken as observed during the same audit and will be checked in next week¡¦s site inspection.

5                                              Environmental Non-Conformance

5.1                                      Summary of Environmental Non-compliance

No non-compliance event was recorded during the reporting period.  Since construction phase impact water quality monitoring has not commenced, no non-compliance of Action and Limit Levels for water quality was recorded during the reporting week.

5.2                                      Summary of Environmental Complaint

No complaint was received during the reporting period. 

5.3                                      Summary of Environmental Summon and successful prosecution

No summons was received during the reporting period.

6                                              Future Key Issues

6.1                                      Key Issues for the Next Reporting Period

Works to be taken for the next reporting period are summarised in Table 6.1.

Table 6.1        Construction Works to Be Taken For the Next Reporting Week

Work to be taken

Submarine Cable Installation

¡P          Cable laying works in Zone A

Landing Point Construction

¡P          Seawall duct work

¡P          Land duct laying works

¡P          Beach manhole construction

Potential environmental impacts arising from the above construction activities are mainly associated with marine water quality, dust, construction noise and waste management.

6.2                                      Monitoring Schedule for the Next Reporting Period

Daily impact water quality monitoring will be conducted in next week and the results will be summarised in the First Weekly Water Quality Impact Monitoring Report.

Next weekly site inspection is temporarily scheduled on 12 October 2012. 

7                                              Conclusions

This First Weekly Site Inspection Report presents the findings of the site inspection and other EM&A activities undertaken during the period from 4 to 7 October 2012, in accordance with the PP (Register No. PP ¡V 452/2011), revised EM&A Manual and the requirements of Environmental Permit (EP- 433/2011). 

Since there were no jetting activities during the reporting period, no construction phase impact water quality and marine mammal monitoring were deemed necessary and hence none was conducted during the reporting period.  No exceedance of Action and Limit Levels of water quality was reported during the reporting period.

A weekly joint environmental site inspection was conducted in the reporting period.  It confirmed that the environmental mitigation measures recommended in the PP were properly implemented by the Contractor.

No non-compliance event was recorded during the reporting period.

No complaint and summons/prosecution was received during the reporting period.

The ET will keep track on the construction works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures.